Category: PMI Agile Certified Practitioner (PMI-ACP)® Exam

Free PMI-ACP® Exam Sample Question 77

On an agile project, the team completed the creation of a potentially shippable product increment. Of the following, which represents the length of time that it took to create this product increment?

Continue Reading

Free PMI-ACP® Exam Sample Question 76

An agile practitioner has developed a prioritized matrix that describes which product features will be delivered in each release over time. What has the agile practitioner created?

Continue Reading

Free PMI-ACP® Exam Sample Question 75

A team lead is currently demonstrating a potentially shippable product increment for project stakeholders. Which agile meeting is being conducted?

Continue Reading

Free PMI-ACP® Exam Sample Question 74

An agile team has decided to create an artifact to demonstrate the product increment for the purpose of gathering feedback from the stakeholders. How should the project team accomplish this task?

Continue Reading

Free PMI-ACP® Exam Sample Question 73

An agile practitioner needs to track the team's performance over time. How might the agile practitioner accomplish this task?

Continue Reading

Free PMI-ACP® Exam Sample Question 72

An agile team is estimating the level of effort necessary to complete their user stories. They decide to make the assumption that the team members will not have any interruptions to project work and will be productive 100% of the time. Which of the following is the team using?

Continue Reading

Free PMI-ACP® Exam Sample Question 71

A product owner and the scrum team members are conducting their first sprint planning meeting. The user stories are read to the team, and the team members have provided estimates to complete these user stories. As the team proceeds to develop the user stories during the sprint, what should the product owner do?

Continue Reading

Free PMI-ACP® Exam Sample Question 70

An agile team does not think it can meet the release deadline based on their velocity midway through the release's iterations. What should the team do?

Continue Reading

Free PMI-ACP® Exam Sample Question 69

An agile team is demonstrating a recently developed product. Who determines when a product is complete?

Continue Reading

Free PMI-ACP® Exam Sample Question 68

An agile team wants to determine the root cause of a recurring issue. Which method would an agile practitioner select to determine the root cause?

Continue Reading

Free PMI-ACP® Exam Sample Question 67

For their new project to develop a point-of-sale system, the team creates an agile model in the form of a sample screen design of the system's user interface. What would an agile practitioner say is the primary benefit of this model?

Continue Reading

Free PMI-ACP® Exam Sample Question 66

An agile team lead has many years of experience and is a subject matter expert on the product that the team is building. How can the team lead best engage the team in solving a problem?

Continue Reading