fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Question

Question 4 years 2 months ago #19884

  • Zohaib Iqbal
  • Zohaib Iqbal's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 4
  • Thank you received: 0
The charter for a project to build a new reward system for the sales division is approved. What should the project manager do now

1. Collect Scope requirement
2. Prepare the scope management plan
3. Develop the scope baseline
4. Develop the project scope statement

Question 4 years 2 months ago #19890

  • Anantha Narayanan Santhanagopalan
  • Anantha Narayanan Santhanagopalan's Avatar
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 39
  • Karma: 3
  • Thank you received: 7
2. Prepare the scope management plan.

Project scope statement is a part of scope baseline which can be done only after defining scope. Collecting the requirement is after the plan is established. So the best answer would be option (2)

Question 4 years 2 months ago #19892

  • googlesmart
  • googlesmart's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 17
  • Karma: 1
  • Thank you received: 10
Correct. You should just start preparing Scope Management Plan. It won't be finished without other items but this is most appropriate option.

Question 4 years 2 months ago #19894

  • Zohaib Iqbal
  • Zohaib Iqbal's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 4
  • Thank you received: 0
In my opinion, The answer should be "Collect scope requirements" because without collect scope requirements it cannot be planned how to manage the scope.
Am I right?

Question 4 years 2 months ago #19896

  • Anantha Narayanan Santhanagopalan
  • Anantha Narayanan Santhanagopalan's Avatar
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 39
  • Karma: 3
  • Thank you received: 7
Zohaib,

Plan scope management states how to collect requirements. So before defining "how to collect" you cannot directly collect requirements.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login