4 years 1 month ago #19896

Anantha Narayanan Santhanagopalan

Anantha Narayanan Santhanagopalan's Avatar

Zohaib,

Plan scope management states how to collect requirements. So before defining "how to collect" you cannot directly collect requirements.
4 years 1 month ago #19894

Zohaib Iqbal

Zohaib Iqbal's Avatar

In my opinion, The answer should be "Collect scope requirements" because without collect scope requirements it cannot be planned how to manage the scope.
Am I right?
4 years 1 month ago #19892

googlesmart

googlesmart's Avatar

Correct. You should just start preparing Scope Management Plan. It won't be finished without other items but this is most appropriate option.
4 years 1 month ago #19890

Anantha Narayanan Santhanagopalan

Anantha Narayanan Santhanagopalan's Avatar

2. Prepare the scope management plan.

Project scope statement is a part of scope baseline which can be done only after defining scope. Collecting the requirement is after the plan is established. So the best answer would be option (2)
4 years 1 month ago #19884

Zohaib Iqbal

Zohaib Iqbal's Avatar

The charter for a project to build a new reward system for the sales division is approved. What should the project manager do now

1. Collect Scope requirement
2. Prepare the scope management plan
3. Develop the scope baseline
4. Develop the project scope statement