In my opinion, The answer should be "Collect scope requirements" because without collect scope requirements it cannot be planned how to manage the scope.
Am I right?
Project scope statement is a part of scope baseline which can be done only after defining scope. Collecting the requirement is after the plan is established. So the best answer would be option (2)