fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Cost Management and Stakeholder - Charter signing Question

Cost Management and Stakeholder - Charter signing Question 8 years 2 months ago #13529

  • Yolanda
  • Yolanda's Avatar Topic Author
  • Visitor
  • Visitor
Good evening,

I am completing my review of the workbooks for the 2 day seminar and encountered quiz responses that were unclear. I need clarification on the following please:

Cost Management Workbook Quiz:
Part of the message is hidden for the guests. Please log in or register to see it.

#5: appears to have an error in the calculation that uses 100 windows being complete when 160 windows are complete. The 40% is correct; the 100 appears to be wrong based on the question. Kindly confirm and/or explain.

#6: I am unclear why the solution uses the new cost of $125,000 at the EAC. I did not see any clues in the question.

Stakeholder question: Why is senior management responsible for signing the charter ref: 5th edition. PMBOK says it is the sponsor.



I look forward to your assistance, please.

Thank you.
Moderators: Yolanda MabutasMarkus KopkoMary Kathrine PaduaProfessor Kevin ReillyJohn Paul BugarinAnusha JayaramHarry ElstonJean KwandaNeil Baghurst PMPElena ZelenevskaiaErik SmithJoseph FlandersPablo Andres Loayza

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login