fbpx

Reply: Cost Management and Stakeholder - Charter signing Question

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : Cost Management and Stakeholder - Charter signing Question

Max. showing the last 6 posts - (Last post first)
6 years 2 weeks ago #13529

Yolanda

's Avatar

Good evening,

I am completing my review of the workbooks for the 2 day seminar and encountered quiz responses that were unclear. I need clarification on the following please:

Cost Management Workbook Quiz:
Part of the message is hidden for the guests. Please log in or register to see it.

#5: appears to have an error in the calculation that uses 100 windows being complete when 160 windows are complete. The 40% is correct; the 100 appears to be wrong based on the question. Kindly confirm and/or explain.

#6: I am unclear why the solution uses the new cost of $125,000 at the EAC. I did not see any clues in the question.

Stakeholder question: Why is senior management responsible for signing the charter ref: 5th edition. PMBOK says it is the sponsor.



I look forward to your assistance, please.

Thank you.

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login