Good evening,
I am completing my review of the workbooks for the 2 day seminar and encountered quiz responses that were unclear. I need clarification on the following please:
Cost Management Workbook Quiz:
Part of the message is hidden for the guests. Please log in or register to see it.
#5: appears to have an error in the calculation that uses 100 windows being complete when 160 windows are complete. The 40% is correct; the 100 appears to be wrong based on the question. Kindly confirm and/or explain.
#6: I am unclear why the solution uses the new cost of $125,000 at the EAC. I did not see any clues in the question.
Stakeholder question: Why is senior management responsible for signing the charter ref: 5th edition. PMBOK says it is the sponsor.
I look forward to your assistance, please.
Thank you.