NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.
  • Page:
  • 1

TOPIC: Looking for an answer

Looking for an answer 1 year 11 months ago #5702

  • Rachel
  • Rachel's Avatar Topic Author
  • Visitor
  • Visitor
Which of the following is not a tool and technique used during the quality control process?

A) Control charts
B ) Statistical Sampling
C) Histogram
D) Quality Audits

The question is from Simplilearn free practice exam

Looking for an answer 1 year 11 months ago #5711

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • PrepCast Instructor
  • Posts: 1087
  • Karma: 34
  • Thank you received: 175
I would say "D".

Quality Audits is a T&T from the Perform Quality Assurance process.
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC

Looking for an answer 1 year 11 months ago #5712

  • Ahmed Amin
  • Ahmed Amin's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 239
  • Karma: 7
  • Thank you received: 49
Hello Rachel,
The answer is D) Quality Audits because it is a tool used in Perform Quality Assurance.

the other 3 tools are used in Control Quality process.

you can check Figure 8-1. Project Quality Management Overview in the PMBOK it clearly includes the above.
Ahmed Amin Abdullah, PMP
Community Moderator
  • Page:
  • 1
Moderators: Yolanda MabutasAhmed AminScott GillardMary Kathrine PaduaERIC BARTLETTKevin NasonMark Wuenscher, PMPTracy Shagnea, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®