8 years 9 months ago #5712

Ahmed Amin

Ahmed Amin's Avatar

Hello Rachel,
The answer is D) Quality Audits because it is a tool used in Perform Quality Assurance.

the other 3 tools are used in Control Quality process.

you can check Figure 8-1. Project Quality Management Overview in the PMBOK it clearly includes the above.
8 years 9 months ago #5711

Cornelius Fichtner

Cornelius Fichtner's Avatar

I would say "D".

Quality Audits is a T&T from the Perform Quality Assurance process.
8 years 9 months ago #5702

Rachel

's Avatar

Which of the following is not a tool and technique used during the quality control process?

A) Control charts
B ) Statistical Sampling
C) Histogram
D) Quality Audits

The question is from Simplilearn free practice exam