Reply: Looking for an answer

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of: Looking for an answer

Max. showing the last 6 posts - (Last post first)
2 years 8 months ago #5712

Ahmed Amin

Ahmed Amin's Avatar

Hello Rachel,
The answer is D) Quality Audits because it is a tool used in Perform Quality Assurance.

the other 3 tools are used in Control Quality process.

you can check Figure 8-1. Project Quality Management Overview in the PMBOK it clearly includes the above.
2 years 8 months ago #5711

Cornelius Fichtner

Cornelius Fichtner's Avatar

I would say "D".

Quality Audits is a T&T from the Perform Quality Assurance process.
2 years 8 months ago #5702

Rachel

's Avatar

Which of the following is not a tool and technique used during the quality control process?

A) Control charts
B ) Statistical Sampling
C) Histogram
D) Quality Audits

The question is from Simplilearn free practice exam

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login
Boost Your PMP Exam Prep in Only Six Hours! Join the Live PMP Coaching Class on Feb 24/25 for just $79. Learn More...
The PMP Exam is Changing in 2018
Simona and Cornelius
Free Interview - Listen Now

This interview with Simona Fallavollita (LinkedIn Profile) was recorded at the magnificient Project Management Institute (PMI)® Global Conference 2017 in Chicago, Illinois. We discuss the how, what, why and when of the changes that are coming to the PMP exam.

Thank you!
Cornelius Fichtner, PMP, CSM