1 year 8 months ago #29678

dev

's Avatar

HI.
Am not able to add screenshot , but for the same question BELOW was PMI response.
Both the stakeholder register and the stakeholder engagement plan need updating. THe stakeholder register identifies all stakeholders and their involvement in the project. THe stakeholder engagement plan is updated to reflect any processes ,procedures,tools aor techniques that affect the engagement of stakeholders in project decision and execution
3 years 8 months ago #22500

Sravanthi TNS, PMP

Sravanthi TNS, PMP's Avatar

Hi Pang Wai Chuen, What was the difficulty level you felt ,of the questions and what is your score in PMI PMP mock test?
The reason I'm asking is - Today I've attempted it and scored 67% which is very less when compared to my scores in Prepcast mock tests which were varying b/w 75% to 80%. Also, I don't see any similarity b/w the questions I see in PMI mock and prepcast simulator questions!! As per my observation, some of the questions lack clarity, ambiguous and some of the questions doesn't relate to any of the options provided!!
One such Ex: One of the questions was asking about to choose a document, but the ans. turned to be a Proj. management Plan!!
I'm trying to take this feedback just for understanding other's opinion who ever has taken this test.
Thanks in advance
3 years 8 months ago #22495

Vivian Johnson

Vivian Johnson's Avatar

Thank you so much!
3 years 8 months ago #22438

Devin

Devin's Avatar

3 years 8 months ago #22437

Vivian Johnson

Vivian Johnson's Avatar

How do I access this PMI PMP Mock Exam. I have searched all over PMI and can't find it.
3 years 9 months ago #22368

Devin

Devin's Avatar

The Question: "A new project manager joins a project during the delivery of a critical milestone. As this has multiple stakeholders, the project manager needs to determine which stakeholders should receive information about the delivery."

The project's stakeholder register should be the complete list of stakeholders. If you look at the many of the processes, one of many of their outputs is often the stakeholder register. During the life of a project we are constantly updating, discovering and refining the register. This is an iterative process which may be initiated through other processes or simply done independently as new stakeholders are discovered (i.e. the company just hired a new VP of something and he/she is now a stakeholder). (PMBOK, pg. 505, emerging trends).

There is no questions that the stakeholder engagement plan and the communication plan are linked, but the PMBOK separates these two processes. You will notice that the stakeholder engagement plan is an INPUT to the communications plan, but not the other way around.

From PMBOK (pg. 522) The stakeholder engagement plan is a component of the project management plan that identifies the strategies and actions required to promote productive involvement of stakeholders in decision making and execution.

PMBOK (pg. 377) - The communications management plan is a component of the project management plan that describes how project communications will be planned, structured, implemented, and monitored for effectiveness.

From a high-level, the stakeholder engagement plan is about "engagement", it is after all THEIR project. The communications plan is how, when, who gets project communications. Releasing project communications can also be sensitive and so the communications plan includes releasing confidential information.

Now to the question. We are wanting to know who should get this project update that we are nearing a critical milestone (which is probably a report). This is clearly in the realm of the communications plan. That being said, how do we actually know who to send the report to? Our communications plan is probably role based and our risk register can be tailored to include project roles or information level (sensitive, weekly status, milestones, financial, vendor, end-user, etc). Thus, any "financial" reports would go to those stakeholders that needed that information (project sponsor, business office, PMO, etc).

Hope this helps.