fbpx

Reply: Question related to resource changes

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : Question related to resource changes

Max. showing the last 6 posts - (Last post first)
3 years 10 months ago #21432

's Avatar

I would go with #2. The Resource Management Plan would tell you how resources are acquired. But in this case the sponsor has assigned somebody to the team. The first step should be to determine if this change impacts the baselines / requires a change request.

Open to other opinions though.
3 years 10 months ago #21430

Question related to resource change

's Avatar

Came across a question that says, a sponsor replaces a key resource with a new hire midway through a project and what should be the response from PM?
The below 2 choices came close,
1/ Refer resource management plan for next course of action
2/ Determine if resource change impacts the project scope, schedule, delivery timelines.

Which among the above options would you choose & why. Appreciate your thoughts.

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login