Question related to resource changes 3 years 10 months ago #21430

  • Question related to resource change
  • Question related to resource change's Avatar Topic Author
  • Visitor
  • Visitor
Came across a question that says, a sponsor replaces a key resource with a new hire midway through a project and what should be the response from PM?
The below 2 choices came close,
1/ Refer resource management plan for next course of action
2/ Determine if resource change impacts the project scope, schedule, delivery timelines.

Which among the above options would you choose & why. Appreciate your thoughts.

Question related to resource changes 3 years 10 months ago #21432

  • Kyle Kilbride
  • Kyle Kilbride's Avatar
  • Visitor
  • Visitor
I would go with #2. The Resource Management Plan would tell you how resources are acquired. But in this case the sponsor has assigned somebody to the team. The first step should be to determine if this change impacts the baselines / requires a change request.

Open to other opinions though.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonKyle KilbrideJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login