Hi ,

1) According to me, answer should be A bcz risk has occured during execution and in execution there is a process called "implement Risk response" and also impact analysis should be conducted as part of PICC process which is after submitting the CR.

2)According to me, answer should be C bcz question states that this is an issue now (fixing issue will increase cost, scope and schedule)which should be analysed as part of PICC process.
3 years 10 months ago #21422

Pierre Paris

Pierre Paris's Avatar

1. A project risk budget was approved by considering high impact risk/ high potential risk. During execution, a risk has occurred which is in risk register but not in the budget. PM response should be:
A. Execute the risk response plan using the available budget.
B. Conduct impact analysis and submit the CR to increase the budget if necessary.

I choose B but answer is A which doesn't make sense for me.


2. A Project initiated based on approved scope and during the implimentation of design a team mate stated a scenario when that the requirements will not me met. fixing issue will increase cost, scope and schedule, there is no money for change. What should PM do?

A. Perform a risk analysis and update the sponsor.
B. Inform the customer and negotiate for risk acceptance.
C. Conduct the PICC process.

Answer is C but i think A. we should first do the analysis and then conduct PICC. Can some one help me on this please....