If it would be me then i would see what the answer is .
1. As per question it sounds like a risk not a issue. Issue should have happened.
2. It is issue and risk as well so depends upon the answer.
3. it again depends upon answer. if you can put the full questions it will help to explain you better...
Risks are identified during Identify Risk process in Planning. However, If Risks are identified during execution do they go to Risk Register or Issue Log ?
Example: There is a concern of schedule delay due to delay in procuring materials in execution phase. (This was identified in execution and not in planning)
Main key developer left the company so there is a probability that schedule might get delayed. (This was identified in execution and not in planning)
Govt Regulations changed are going to impact the project costs while the project is in execution. (This was identified in execution and not in planning)
Should these be entered in Issue Log or Risk Register ?