fbpx

Reply: Risk Register vs Issue Log

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : Risk Register vs Issue Log

Max. showing the last 6 posts - (Last post first)
3 years 10 months ago #21439

JIGAR PANCHAL

JIGAR PANCHAL's Avatar

I believe first we identify the issue in the log and then can follow the proper channel from Risk Management Plan to revise it.
3 years 10 months ago #21426

Pierre Paris

Pierre Paris's Avatar

Hi Neha,

If it would be me then i would see what the answer is .

1. As per question it sounds like a risk not a issue. Issue should have happened.
2. It is issue and risk as well so depends upon the answer.
3. it again depends upon answer. if you can put the full questions it will help to explain you better...
3 years 10 months ago #21410

Neha Talavdekar

Neha Talavdekar's Avatar

Risks are identified during Identify Risk process in Planning. However, If Risks are identified during execution do they go to Risk Register or Issue Log ?

Example: There is a concern of schedule delay due to delay in procuring materials in execution phase. (This was identified in execution and not in planning)
Main key developer left the company so there is a probability that schedule might get delayed. (This was identified in execution and not in planning)
Govt Regulations changed are going to impact the project costs while the project is in execution. (This was identified in execution and not in planning)

Should these be entered in Issue Log or Risk Register ?

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login