fbpx

The PM PrepCast is closing. All product access ends December 4, 2026.
Until October 31, all products are 50% off.
Read the announcement

Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Explanation

Explanation 6 years 3 months ago #21314

  • Anonymous
  • Anonymous's Avatar Topic Author
  • Visitor
  • Visitor
How did they get this answer?

A project was planned to take 5 months. The team is currently 3 months into it and has completed half of the work.

Applying Earned schedule technique, what are the performance data of the project?


SV: -0.5 months, SPI: 0.83
SV: 1.5 months, SPI: 1.5
SV: -2,5 months, SPI: 0.83
SV: 0.5 months, SPI: 1.83

Explanation 6 years 3 months ago #21327

  • Harry Elston
  • Harry Elston's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 607
  • Karma: 40
  • Thank you received: 169
Anon:

This is one of the questions that look like a math question bu really isn't as long as you know the definitions of all the performance indices and variances.

The project is 50% complete and 60% into the schedule. It is BEHIND Schedule - therefore the project's SPI is less than 1. Therefore only A or C can be correct.
In terms of time they are at 2.5 months worth of earned value but they have burned 3 months of Planned Value. Therefore they are -0.5 months in Schedule Variance.

The answer is A

Hope that helps.

Harry
+++++
Harry J. Elston, Ph.D., CIH, PMP
Last edit: by Harry Elston.

Explanation 6 years 1 month ago #22422

  • Anonymous
  • Anonymous's Avatar Topic Author
  • Visitor
  • Visitor
Let me explain.
We have completed half the work. As per the plan, 100% work <=> 5 months
So, 50% work <=> 2.5 months

2.5 months is the Earned Schedule.
3.0 months is the Actual Time.

Accordingly,
SV = ES - AT = -0.5 months
SPI = ES/AT = 0.83

A is the correct choice.

If you wish to understand the basics of Earned Schedule, have a look at this lesson.
Moderators: Yolanda MabutasMarkus KopkoMary Kathrine PaduaProfessor Kevin ReillyJohn Paul BugarinAnusha JayaramHarry ElstonJean KwandaNeil Baghurst PMPElena ZelenevskaiaErik SmithJoseph FlandersPablo Andres Loayza

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login