TOPIC: SPI on Critical Path

SPI on Critical Path 3 years 10 months ago #21313

  • Marc
  • Marc's Avatar Topic Author
  • Visitor
  • Visitor
What would the status be if the overall SPI is 1.8 and the critical path SPI is .70?

Behinde schedule?
Ahead of schedule?

SPI on Critical Path 3 years 10 months ago #21321

  • Eric Wanyutu Kahiga, PMP, PMI-ACP
  • Eric Wanyutu Kahiga, PMP, PMI-ACP's Avatar
  • Offline
  • Expert Boarder
  • Expert Boarder
  • Posts: 84
  • Karma: 4
  • Thank you received: 28
Hi Marc.

Whenever the critical path Schedule Performance Index (SPI) is below 1.0 the entire project is late. In this case, the (SPI) that is important is 0.7 and it means that the project is behind schedule. I hope that helps.
Eric Wanyutu

SPI on Critical Path 3 years 10 months ago #21341

  • Marc Vazquez
  • Marc Vazquez's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
Thank you Eric,

That was exactly my logic as well but then I started to overthink it. Could you say that the status of the project is ahead of schedule but at risk or because the Critical Path is below 1, then the whole project behind schedule?

Thank you for your reply!
Currently doing some last minute prep before my exam.

SPI on Critical Path 3 years 10 months ago #21360

  • Eric Wanyutu Kahiga, PMP, PMI-ACP
  • Eric Wanyutu Kahiga, PMP, PMI-ACP's Avatar
  • Offline
  • Expert Boarder
  • Expert Boarder
  • Posts: 84
  • Karma: 4
  • Thank you received: 28
Hi Marc.
You are very welcome. As you do your last-minute preparations for the exam, keep your eyes on the ball and do not overthink. Ignore any extraneous information that is especially common on the lengthy PMP questions and concentrate on the "ASK". I wish you all the best.
Eric Wanyutu

SPI on Critical Path 3 years 10 months ago #21363

  • Junior
  • Junior's Avatar Topic Author
  • Visitor
  • Visitor
I had same question too. What’s the right answer, Behind schedule, Ahead of Schedule, Ahead of Schedule with risk.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login