Hi Marc.
You are very welcome. As you do your last-minute preparations for the exam, keep your eyes on the ball and do not overthink. Ignore any extraneous information that is especially common on the lengthy PMP questions and concentrate on the "ASK". I wish you all the best.
That was exactly my logic as well but then I started to overthink it. Could you say that the status of the project is ahead of schedule but at risk or because the Critical Path is below 1, then the whole project behind schedule?
Thank you for your reply!
Currently doing some last minute prep before my exam.
Whenever the critical path Schedule Performance Index (SPI) is below 1.0 the entire project is late. In this case, the (SPI) that is important is 0.7 and it means that the project is behind schedule. I hope that helps.