TOPIC: Duplicated resource information

Duplicated resource information 3 years 10 months ago #21260

  • W Pontius
  • W Pontius's Avatar Topic Author
  • Visitor
  • Visitor
What is the difference between the information contained in each of the Physical Resource Requirements, the Resource Breakdown Structure, and the Resource Requirements, and why are all 3 needed as inputs to the Control Resources process? As best I can determine, the information contained in these 3 is the same.
Thank you.

Duplicated resource information 3 years 10 months ago #21265

  • Devin
  • Devin's Avatar
  • Offline
  • Expert Boarder
  • Expert Boarder
  • Posts: 93
  • Karma: 10
  • Thank you received: 52
The key is to answering your question is to understand just what the CONTROL RESOURCES process is trying to accomplish: Control Resources is the process of ensuring that the physical resources assigned and allocated to the project are available as planned, as well as monitoring the planned versus actual utilization of resources and taking corrective action as necessary.

Physical resource assignments - The physical resource assignments describe the expected resource utilization along with details such as type, amount, location, and whether the resource is internal to the organization or outsourced.
Resource breakdown structure - The resource breakdown structure provides a reference in case any resource needs to be replaced or reacquired during the course of the project. (corrective action).
Resource requirements - Resource requirements identify the needed material, equipment, supplies, and other resources. Planned resources.

In broadest terms, these inputs give the fullest picture of the available resources, planned resources and their utilization.

Hope this helps.

Duplicated resource information 3 years 10 months ago #21266

  • Wesley Pontius
  • Wesley Pontius's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
Thank you for responding, but it's still unclear to me. For example, if the Physical Resource Assignment (PRA) includes all the information about the resources needed (including location, etc), why would you need the Resource Breakdown Structure? Why not get the same information from the PRA in the event replacement or reacquisition is necessary? What aspect of Control Resources can't be ascertained by the PRA?
I suspect I'm missing something simple.

Duplicated resource information 3 years 10 months ago #21271

  • Devin
  • Devin's Avatar
  • Offline
  • Expert Boarder
  • Expert Boarder
  • Posts: 93
  • Karma: 10
  • Thank you received: 52
The RBS is the only one that is linked to the WBS. Without the RBS you don't have a resource to work package linkage, which the others don't have. So it would be difficult to control resources when you don't know what they are being used for or working on.
The following user(s) said Thank You: Wesley Pontius
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login