4 years 2 days ago #20472

Harry Elston

Harry Elston's Avatar

Kin,

In general, anything that will change the scope, cost or schedule baselines will require a formal change request to be approved by the Change Control Board.

Harry
4 years 2 days ago #20471

Anonymous

's Avatar

It is C
4 years 2 days ago #20470

Kin

Kin's Avatar

Hello,
I have got across this question and I have no idea what's the answer. It is confusing somehow. (D) sounds correct but, there are new requirements added, that could mean changes on Scope which requires a change request which leaves us to (C). But, again, there are documents that do not need a change Request like Risk Register for instance, which makes (C) not the best answer? And leaves us for ( B )? I have no idea. Any help, please?