TOPIC: Project documents and change request

Project documents and change request 5 months 3 weeks ago #20470

  • Kin
  • Kin's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
Hello,
I have got across this question and I have no idea what's the answer. It is confusing somehow. (D) sounds correct but, there are new requirements added, that could mean changes on Scope which requires a change request which leaves us to (C). But, again, there are documents that do not need a change Request like Risk Register for instance, which makes (C) not the best answer? And leaves us for ( B )? I have no idea. Any help, please?
Attachments:
Last edit: by Kin.

Project documents and change request 5 months 3 weeks ago #20471

  • Anonymous
  • Anonymous's Avatar
  • Visitor
  • Visitor
It is C

Project documents and change request 5 months 3 weeks ago #20472

  • Harry Elston
  • Harry Elston's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 245
  • Karma: 16
  • Thank you received: 78
Kin,

In general, anything that will change the scope, cost or schedule baselines will require a formal change request to be approved by the Change Control Board.

Harry
+++++
Harry J. Elston, Ph.D., CIH, PMP
Last edit: by Harry Elston.
Moderators: Yolanda MabutasMary Kathrine PaduaCynthia Lim Louis, PMPTracy Shagnea, PMPGabriella Dellino, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinAmy MartinezEmily Rivera, PMPLisa Sweeney PMPHarry ElstonMani SelvanDenver MartinEric Wanyutu Kahiga, PMPSarah FucciThiago França, PMP®Felix Kamanga, PMPChan RampersaudElena MekhanoshinaKyle Kilbride, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login