4 years 1 month ago #20026

Zara Rizwan

Zara Rizwan's Avatar

I also believe that the answer is 4. Distribute the approved project charter.
4 years 1 month ago #19897

Anantha Narayanan Santhanagopalan

Anantha Narayanan Santhanagopalan's Avatar

4. Distribute the approved project charter ??
4 years 1 month ago #19895

Zohaib Iqbal

Zohaib Iqbal's Avatar

A project manager is ready to start a new project that has a clearly defined scope, assumptions and constraints. What should the project manager do to ensure that all key stakeholders have a common understanding of the project's scope and deliverable?

1. Send Weekly project status report
2. Apply the action plan used in previous projects to prevent issues
3. Hold a product scope definition meeting with the client
4. Distribute the approved project charter