Question regarding experience for application 4 weeks 1 day ago #19448

  • Muhammad Awais
  • Muhammad Awais's Avatar Topic Author
  • Away
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 13
  • Thank you received: 0
Hi,
I have worked as project engineer for electrical department for last 4 years. I have managed as well as programmed the machines as well. I was involved in planning phase with the customer about required electrical equipment and required functions of machine to be programmed. My question is regarding execution phase. During execution I not only coordinated with electrical installation team about installation but the programming I have done myself. In pmp application if I write the programming experience in execution phase, will it be counted as valid execution experience?
Later in monitoring and controlling phase I lead my team on site for commissioning and testing of machine. In closing phase I conducted test production with customer and provided training to the operators.
Thanks for the reply in advance
Best regards
Awais

Question regarding experience for application 4 weeks 1 day ago #19452

  • Joe Pang
  • Joe Pang's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 211
  • Karma: 13
  • Thank you received: 64
Hi Muhammad,

The programming in your execution phase of your project looks like one of the work package, and performing tasks within a WP does not count towards PM experience.

This doesn't make you any less of a project manager though, as many PMs are very hands on. It only means that the programming task is not eligible on the PMP application.

Hope this helps,
Joe
Toronto-based project manager, I specialize in Capital Projects and Digital Transformation Projects for the power & utility sector.

I welcome all types of collaboration opportunities, feel free to connect with me on Linkedin

Question regarding experience for application 4 weeks 1 day ago #19455

  • Muhammad Awais
  • Muhammad Awais's Avatar Topic Author
  • Away
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 13
  • Thank you received: 0
Thanks for reply Joe.
One more question :
As I only handled the electrical aspect of the machine installation and commissioning, is that any problem for application. For mechanical and Construction there were other teams.

Question regarding experience for application 4 weeks 1 day ago #19456

  • Muhammad Awais
  • Muhammad Awais's Avatar Topic Author
  • Away
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 13
  • Thank you received: 0
Thanks for reply Joe.
One more question :
As I only handled the electrical aspect of the machine installation and commissioning, is that any problem for application. For mechanical and Construction there were other teams.

Question regarding experience for application 3 weeks 5 days ago #19479

  • Joe Pang
  • Joe Pang's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 211
  • Karma: 13
  • Thank you received: 64
Hi Muhammad, no problem you can focus on the electrical aspect
Toronto-based project manager, I specialize in Capital Projects and Digital Transformation Projects for the power & utility sector.

I welcome all types of collaboration opportunities, feel free to connect with me on Linkedin
Moderators: Yolanda MabutasScott GillardMary Kathrine PaduaCynthia Lim Louis, PMPTracy Shagnea, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinAmy MartinezEmily Rivera, PMPLisa Sweeney PMPHarry ElstonMani Selvan

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login
Boost Your PMP Exam Prep in Only Eight Hours! Join the Live PMP Coaching Class on January 18/19 for just $179. Click to learn more... OR Click to watch a free session...