fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: In which process is Change Log first created?

In which process is Change Log first created? 4 years 4 months ago #19227

  • Marta
  • Marta's Avatar Topic Author
  • Visitor
  • Visitor
As change control tools assume particular importance at Perform Integrated Change Control, is the Change Log one of these tools and first created in this process?
Cannot find it explicity mentioned on PMBOK.
Many thanks.

In which process is Change Log first created? 4 years 4 months ago #19229

  • Harry Elston
  • Harry Elston's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 457
  • Karma: 27
  • Thank you received: 144
I could not find that in the PMBOK either, but the logical place for it to be created is with the change management plan, as that is the plan that tells the project organization how to execute changes.

Other mods may have better answers.
+++++
Harry J. Elston, Ph.D., CIH, PMP

In which process is Change Log first created? 4 years 4 months ago #19230

  • Joe Pang
  • Joe Pang's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 250
  • Karma: 24
  • Thank you received: 99
You're correct Marta, the PMBOK did not mention specifically when the change log is created.

I want to second Harry that the Planning - Project Management Plan process is the best time to create the change log, since by that time you will have an idea of what type of changes you will be expecting.

Best,
Joe
Toronto-based project manager, I specialize in capital construction projects and digital transformation projects for the power & utility sector.

I welcome all types of collaboration opportunities, feel free to connect with me on Linkedin
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP