4 years 4 months ago #19203

Paolo Santinelli

Paolo Santinelli's Avatar

Dear PM PrepCast Team,

I would like to ask you an additional clarification about two topics:

- EAC formulas
- Process Groups

Abtou the EAC formulas, I am comfortable about the formulas, I have no problems in remembering all of them but while practicing them I found out a certain level of uncertainty on the criteria to apply them.
Could be possible to have a clear criteria to use them. For example, does it make sense considering the CPI value as a criteria to select which formula to use. I mean:
- If CPI less than 1, EAC = BAC/CPI
- If CPI higher than 1, EAC= AC +(BAC-EV)
- If both CPI and SPI are lower than 1, EAC= AC + (BAC-EV)/(CPI*SPI)

About the Process Group, it is clear that exist a hierarchy between them: all the Initiating processes must be completed before moving to the Planning Group and so on. However, does exist a precedence within a specific Process Group? For example, in an easy case, the Initiating Group has two processes: Develop Charter and Identify Stakeholder. Based on my understanding, Develop Charter should be the first process, followed by Identify Stakeholder. However, in some questions' answers I found out that Identify Stakeholder ( and therefore the Stakeholder Register) could be ready before the Charter is developed. The same comment applies to the other Process Group.