TOPIC: Is it the right answer ?

Is it the right answer ? 2 weeks 1 day ago #19201

  • Jaydip Chakrabarti
  • Jaydip Chakrabarti's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 13
  • Thank you received: 1
Hello all,

Question :

You are in charge of a project that deals with laying out a lavish 18 hole golf course.The project work is in progress.You also have a number of contractors working on the project.Being an experienced manager you know that communication is key to success of the project.You have identified 10 stakeholders with whom you need to communicate.Due to some internal and external organizational changes at the client end three new stakeholders have been added with whom you need to communicate with.You also had to reduce one of the contractors with whom you were communicating.How many communication channels do you have now?
A. 45
B. 78
C. 91
D. 66

I thought the right answer was B but the site says D. Can someone please explain why ?

Is it the right answer ? 2 weeks 18 hours ago #19204

  • Elizabeth Harrin
  • Elizabeth Harrin's Avatar
  • Offline
  • Administrator
  • Administrator
  • Posts: 52
  • Karma: 2
  • Thank you received: 9
Hello Jaydip
Did you find this question in The PM Exam Simulator? In the Simulator, you can see the explanation for the answer.

Having looked into the debate online around this question, the confusion comes from whether the PM is included in the calculation or not. As the question says, "You have identified 10 stakeholders with whom you need to communicate," I interpret this to mean you should add in the PM to the calculation on top of the original 10 stakeholders.
---
Elizabeth Harrin

Is it the right answer ? 2 weeks 15 hours ago #19207

  • Jaydip Chakrabarti
  • Jaydip Chakrabarti's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 13
  • Thank you received: 1
Hi Elizabeth,

I got the question from www.certchamp.com . Had similar question from other site and there, they added PM in the calculation. What is the best way of getting clarification

Is it the right answer ? 1 week 6 days ago #19209

  • Elizabeth Harrin
  • Elizabeth Harrin's Avatar
  • Offline
  • Administrator
  • Administrator
  • Posts: 52
  • Karma: 2
  • Thank you received: 9
You need to be able to interpret the question yourself. Read the question carefully and you will see that the PM is not included in the original numbers and therefore needs to be added to the formula.
---
Elizabeth Harrin
Moderators: Yolanda MabutasScott GillardMary Kathrine PaduaCynthia Lim Louis, PMPTracy Shagnea, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinAmy MartinezEmily RiveraLisa Sweeney PMPHarry ElstonMani Selvan

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login
Boost Your PMP Exam Prep in Only Eight Hours! Join the Live PMP Coaching Class on December 21/22 for just $179. Click to learn more... OR Click to watch a free session...