fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: May approved change requests be implemented in "Control Quality" process?

May approved change requests be implemented in "Control Quality" process? 4 years 5 months ago #18839

  • Eric Hu
  • Eric Hu's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 17
  • Thank you received: 1
In lesson L04.06.3 "Perform Integrated Change Control Part 3", the "Takeways" mentioned approved change requests are implemented via 3 processes:
1. Direct and Manage project work
2. Control Quality
3. Control Procurement
According to PMBOK page 298 "Control Quality is the process of monitoring and recording results of executing the quality management activities in order to access performance and ensure the project outputs are complete, correct and meet customer expectations", it's not doing any implementation.
PMBOK 8.3.1.3 mentioned "The implementation of approved changes should be verified, confirmed for completeness, retested, and certified as correct".
It sounds "control quality" process only verifies "approved change request", doesn't do any implementation.

Any suggestions?

May approved change requests be implemented in "Control Quality" process? 4 years 5 months ago #18850

  • Tracy Shagnea, PMP
  • Tracy Shagnea, PMP's Avatar
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 134
  • Karma: 7
  • Thank you received: 46
Hi Eric,

The key here is that "Direct and Manage Project Work" includes leading AND doing the work. One of the outputs is the Deliverable itself. After that you move on to Control Quality.

I believe this answers your question...

Regards,
Tracy
Forum Moderator
PMP, CSM, M.S. Management
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login