TOPIC: Question 35: self assessment-needs clarifications

Question 35: self assessment-needs clarifications 6 years 7 months ago #18735

  • Nadia Zandaqi
  • Nadia Zandaqi's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 0
Hi Dears,

I notice that in Question 35: self assessment Q&A the Answer is A, but if I go to the Reference: A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) 248, 252 , it mentioned the project budget = cost baseline + Management reserve ; so I feel there is a contradiction , can any one clarify this point for me.

Best Regards,
Nadia

Question 35: self assessment-needs clarifications 6 years 6 months ago #18824

  • Jenikka Ebias
  • Jenikka Ebias's Avatar
  • Visitor
  • Visitor
Hi Nadia,

Here's a response from one of our resident Project Management Professionals:

"There is no contradiction. The cost baseline is the approved version of the time-phased budget that includes contingency reserves but not management reserves."

Hope this helps clarify your concern. Have a good day!
Moderators: Yolanda MabutasMarkus KopkoMary Kathrine PaduaProfessor Kevin ReillyJohn Paul BugarinAnusha JayaramHarry ElstonJean KwandaNeil Baghurst PMP, CSM, DFFS Black BeltElena ZelenevskaiaErik SmithJoseph FlandersPablo Andres Loayza

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login