fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Question 35: self assessment-needs clarifications

Question 35: self assessment-needs clarifications 4 years 5 months ago #18735

  • Nadia Zandaqi
  • Nadia Zandaqi's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 0
Hi Dears,

I notice that in Question 35: self assessment Q&A the Answer is A, but if I go to the Reference: A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) 248, 252 , it mentioned the project budget = cost baseline + Management reserve ; so I feel there is a contradiction , can any one clarify this point for me.

Best Regards,
Nadia

Question 35: self assessment-needs clarifications 4 years 5 months ago #18824

  • Jenikka Ebias
  • Jenikka Ebias's Avatar
  • Visitor
  • Visitor
Hi Nadia,

Here's a response from one of our resident Project Management Professionals:

"There is no contradiction. The cost baseline is the approved version of the time-phased budget that includes contingency reserves but not management reserves."

Hope this helps clarify your concern. Have a good day!
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login