Reply: EVM - for EV do we count partial work? Or only count when it is complete?

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : EVM - for EV do we count partial work? Or only count when it is complete?

Max. showing the last 6 posts - (Last post first)
4 years 6 months ago #18429

James Keuning

James Keuning's Avatar

PrepCast lesson 0705.1 pretty clearly states more than once that EV only includes work that is completed in full. Not partially completed. Completed.

But then question 625116 adds up the EV of three activities and uses .5xPV to calculate the EV of work that is 50% complete.

What am I missing?