TOPIC: EVM - for EV do we count partial work? Or only count when it is complete?

EVM - for EV do we count partial work? Or only count when it is complete? 2 weeks 1 day ago #18429

  • James Keuning
  • James Keuning's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 7
  • Thank you received: 0
PrepCast lesson 0705.1 pretty clearly states more than once that EV only includes work that is completed in full. Not partially completed. Completed.

But then question 625116 adds up the EV of three activities and uses .5xPV to calculate the EV of work that is 50% complete.

What am I missing?
Last edit: by James Keuning.
Moderators: Yolanda MabutasScott GillardMary Kathrine PaduaSteven Mudrinich, PMPCynthia Lim Louis, PMPTracy Shagnea, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinJason YorekLuke HoSimone ChristieAmy MartinezDaniel DewartEmily RiveraMani Selvan

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login
Boost Your PMP Exam Prep in Only Eight Hours! Join the Live PMP Coaching Class on September 21/22 for just $179. Click to learn more... OR Click to watch a free session...