fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: EVM - for EV do we count partial work? Or only count when it is complete?

EVM - for EV do we count partial work? Or only count when it is complete? 4 years 7 months ago #18429

  • James Keuning
  • James Keuning's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 20
  • Karma: 1
  • Thank you received: 4
PrepCast lesson 0705.1 pretty clearly states more than once that EV only includes work that is completed in full. Not partially completed. Completed.

But then question 625116 adds up the EV of three activities and uses .5xPV to calculate the EV of work that is 50% complete.

What am I missing?
Last edit: by James Keuning.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login