Reply: Why Approved Change Request is input to the Control Quality?

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : Why Approved Change Request is input to the Control Quality?

Max. showing the last 6 posts - (Last post first)
4 years 8 months ago #17876

Donald Terry

Donald Terry's Avatar

Hi Aarati,

Actually, approved change requests are an input to the Direct and Manage Project Work process (page 93 of the PMBOK® Guide).

As far as approved change requests as an input to the Control Quality process, there is a good description on page 301 of the PMBOK® Guide. As an example, let's say that a project deliverable was found to be defective, and a change request was submitted to repair the defect. Once approved, the approved change request might be used as an input to the Control Quality process to ensure the defect repair was performed in conformance with quality standards and the repaired deliverable passes any applicable quality control testing.
4 years 8 months ago #17870

Aarati Sonkusare

Aarati  Sonkusare's Avatar

I am trying to understand why Approved Change Request is an input to the Control Quality and not to the Direct and Manage Project work. As I understand change requests are first approved by CCB anf then they are implemented.