4 years 10 months ago #17579

Cynthia Lim Louis, PMP

Cynthia Lim Louis, PMP's Avatar

Basis of estimates = how the cost is derived.
Cost estimates = the estimated cost that are included to complete an activity.
Duration estimates = the estimated time period required to complete an activity
4 years 10 months ago #17510

Jessica Aweya

Jessica Aweya's Avatar

Hello,

What is the difference between the basis of estimates, cost estimates and duration of estimates?

Thanks