TOPIC: Basis of estimates vs Cost Estimates

Basis of estimates vs Cost Estimates 1 year 2 months ago #17510

  • Jessica Aweya
  • Jessica Aweya's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
Hello,

What is the difference between the basis of estimates, cost estimates and duration of estimates?

Thanks

Basis of estimates vs Cost Estimates 1 year 2 months ago #17579

  • Cynthia Lim Louis, PMP
  • Cynthia Lim Louis, PMP's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 84
  • Karma: 4
  • Thank you received: 17
Basis of estimates = how the cost is derived.
Cost estimates = the estimated cost that are included to complete an activity.
Duration estimates = the estimated time period required to complete an activity
Moderators: Yolanda MabutasMary Kathrine PaduaCynthia Lim Louis, PMPTracy Shagnea, PMPGabriella Dellino, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinAmy MartinezEmily Rivera, PMPMohammad Alharbi, PMP, PMI-ACPLisa Sweeney PMPHarry ElstonMani SelvanDenver MartinEric Wanyutu Kahiga, PMPSarah FucciThiago França, PMP®Felix Kamanga, PMPChan RampersaudKyle Kilbride, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login
Get PMP Exam Ready in Just Four Weeks! Join the Live PMP Blended Training Course Starting August 10. Click to learn more...