fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Basis of estimates vs Cost Estimates

Basis of estimates vs Cost Estimates 6 years 11 months ago #17510

  • Jessica Aweya
  • Jessica Aweya's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
Hello,

What is the difference between the basis of estimates, cost estimates and duration of estimates?

Thanks

Basis of estimates vs Cost Estimates 6 years 11 months ago #17579

  • Cynthia Lim Louis, PMP
  • Cynthia Lim Louis, PMP's Avatar
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 84
  • Karma: 5
  • Thank you received: 21
Basis of estimates = how the cost is derived.
Cost estimates = the estimated cost that are included to complete an activity.
Duration estimates = the estimated time period required to complete an activity
The following user(s) said Thank You: Joann Sosa, Divya Singh
Moderators: Yolanda MabutasMarkus KopkoMary Kathrine PaduaProfessor Kevin ReillyJohn Paul BugarinAnusha JayaramHarry ElstonJean KwandaNeil Baghurst PMP, CSM, DFFS Black BeltElena ZelenevskaiaErik SmithJoseph FlandersPablo Andres Loayza

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login