Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Basis of estimates vs Cost Estimates

Basis of estimates vs Cost Estimates 6 months 3 weeks ago #17510

  • Jessica Aweya
  • Jessica Aweya's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
Hello,

What is the difference between the basis of estimates, cost estimates and duration of estimates?

Thanks

Basis of estimates vs Cost Estimates 6 months 1 week ago #17579

  • Cynthia Lim Louis, PMP
  • Cynthia Lim Louis, PMP's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 84
  • Karma: 3
  • Thank you received: 17
Basis of estimates = how the cost is derived.
Cost estimates = the estimated cost that are included to complete an activity.
Duration estimates = the estimated time period required to complete an activity
Moderators: Yolanda MabutasScott GillardMary Kathrine PaduaCynthia Lim Louis, PMPTracy Shagnea, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinAmy MartinezEmily RiveraLisa Sweeney PMPHarry ElstonMani Selvan

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login
Boost Your PMP Exam Prep in Only Eight Hours! Join the Live PMP Coaching Class on December 21/22 for just $179. Click to learn more... OR Click to watch a free session...