Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Lessons Learned in Multi-Phase projects

Lessons Learned in Multi-Phase projects 5 months 6 days ago #17400

  • Ben Chalfie
  • Ben Chalfie's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 41
  • Thank you received: 0
Are lessons learned transferred to the lessons learned repository at the end of each phase?

Lessons Learned in Multi-Phase projects 5 months 5 days ago #17428

  • Cynthia Lim Louis, PMP
  • Cynthia Lim Louis, PMP's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 80
  • Karma: 1
  • Thank you received: 17
First you transferred to a Lesson Learned Register and when it is finalized, you transferred to Lessons Learned Repository at the end of each phase.

Lessons Learned in Multi-Phase projects 2 weeks 3 days ago #18628

  • Kalpesh Patil
  • Kalpesh Patil's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 4
  • Thank you received: 0
Dear Cornelis and PMP Experts,
first phase is completed and project is now in second phase.
If I need to check lesson learnt in first phase then where I have to review
1- Lesson learned register of first phase ?
1- Lesson learned repository of first phase ?

I always have confusion for multi-phase project that..... after first phase completion is there lesson learned register or Lesson learned repository.

Please let me know your view.
Thanks.

Lessons Learned in Multi-Phase projects 2 weeks 3 days ago #18629

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Away
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1553
  • Karma: 52
  • Thank you received: 280
Kalpesh,

Please turn to the PMBOK Guide 6th edition page 709 and review the definition of Lessons Learned Register and Repository.

Now that you have reviewed this... what would YOU say is the answer?
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC

Lessons Learned in Multi-Phase projects 2 weeks 3 days ago #18630

  • Kalpesh Patil
  • Kalpesh Patil's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 4
  • Thank you received: 0
Page no. 709 - lesson learned repository is a store of historical information about lesson learned in project.
Its about only project, not clear about phase.
Now I am in second phase and I need to check lesson learnt in first phase of multi-phase project then where I have to review.
1- Lesson learned register of first phase ?
1- Lesson learned repository of first phase ?
Moderators: Yolanda MabutasScott GillardMary Kathrine PaduaSteven Mudrinich, PMPCynthia Lim Louis, PMPTracy Shagnea, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinJason YorekLuke HoSimone ChristieAmy MartinezDaniel DewartEmily RiveraMani Selvan

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login