Reply: Change Request for Stakeholder Register Update?

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : Change Request for Stakeholder Register Update?

Max. showing the last 6 posts - (Last post first)
7 years 5 months ago #17324

Cynthia Lim Louis, PMP

Cynthia Lim Louis, PMP's Avatar

Stakeholder register is a project document that needs to be updated (no need change request) whenever there is any change in stakeholder information. In this register, it captures stakeholders requirements and expectations of the project, if there is any change in stakeholder requirements and expectations that affect the project management plan, then change request is required.
7 years 5 months ago #17306

Ben Chalfie

Ben Chalfie's Avatar

Let's say your project is midway through. Would you need to issue a change request to update the stakeholder register?