Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Change Request for Stakeholder Register Update?

Change Request for Stakeholder Register Update? 3 months 1 week ago #17306

  • Ben Chalfie
  • Ben Chalfie's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 41
  • Thank you received: 0
Let's say your project is midway through. Would you need to issue a change request to update the stakeholder register?

Change Request for Stakeholder Register Update? 3 months 1 week ago #17324

  • Cynthia Lim Louis, PMP
  • Cynthia Lim Louis, PMP's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 80
  • Thank you received: 16
Stakeholder register is a project document that needs to be updated (no need change request) whenever there is any change in stakeholder information. In this register, it captures stakeholders requirements and expectations of the project, if there is any change in stakeholder requirements and expectations that affect the project management plan, then change request is required.
Moderators: Yolanda MabutasScott GillardMary Kathrine PaduaSteven Mudrinich, PMPCynthia Lim Louis, PMPTracy Shagnea, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinJason YorekLuke HoSimone ChristieAmy MartinezDaniel DewartEmily Rivera

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login
Boost Your PMP Exam Prep in Only Eight Hours! Join the Live PMP Coaching Class on August 24/25 for just $179. Click to learn more... OR Click to watch a free session...