Let's say your project is midway through. Would you need to issue a change request to update the stakeholder register?

Change Request for Stakeholder Register Update? 8 months 1 week ago #17324

  • Cynthia Lim Louis, PMP
  • Cynthia Lim Louis, PMP's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 84
  • Karma: 3
  • Thank you received: 17
Stakeholder register is a project document that needs to be updated (no need change request) whenever there is any change in stakeholder information. In this register, it captures stakeholders requirements and expectations of the project, if there is any change in stakeholder requirements and expectations that affect the project management plan, then change request is required.
Moderators: Yolanda MabutasScott GillardMary Kathrine PaduaCynthia Lim Louis, PMPTracy Shagnea, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinAmy MartinezEmily Rivera, PMPLisa Sweeney PMPHarry ElstonMani Selvan

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login
Boost Your PMP Exam Prep in Only Eight Hours! Join the Live PMP Coaching Class on January 18/19 for just $179. Click to learn more... OR Click to watch a free session...