TOPIC: Relationship between Corrective Actions and Change Requests

Relationship between Corrective Actions and Change Requests 4 years 11 months ago #17305

  • Ben Chalfie
  • Ben Chalfie's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 41
  • Thank you received: 0
If I decide to implement a schedule compression technique, do I need to submit a change request even though I know the results of that action won't change my schedule baseline? Put another way, do you submit change requests when you're unsure if an action in a particular knowledge area will affect the baseline or planned performance of another knowledge area?

Relationship between Corrective Actions and Change Requests 4 years 11 months ago #17323

  • Cynthia Lim Louis, PMP
  • Cynthia Lim Louis, PMP's Avatar
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 84
  • Karma: 5
  • Thank you received: 21
When you use a schedule compression technique, chances are you know you are not going to meet a deadline, and so even though it won't affect your schedule baseline, using this technique typically result in increased risk and/or costs. Therefore, in reality, project manager will do some initial calculation and risk analysis (e.g., staff acquisition, cost of overtime, etc.) to see whether it is viable to use this technique. If there is any impact in cost, change request is needed. If there is no effect (which is very highly unlikely) with any of the baselines , then you don't have to submit a change request.

Relationship between Corrective Actions and Change Requests 4 years 11 months ago #17333

  • Ben Chalfie
  • Ben Chalfie's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 41
  • Thank you received: 0
Thanks Cynthia. What's the breakdown of responsibility between the project manager and CCB for analyzing the impact of a change request on other constraints? I'm looking at Rita's book, and it implies that the project manager only examines the impact of a change within a particular knowledge area before submitting a change request. Is the project manager still involved with analyzing impacts on other project areas and identifying the best corrective action even after submitting the change request?
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login