Quality Data vs. Quality Control Measurements 5 years 5 months ago #17171

  • Ben Chalfie
  • Ben Chalfie's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 41
  • Thank you received: 0
In regards to quality management, is there a difference against what's compared with the quality metrics during performance review during the Manage Quality process and quality control measurements?

Quality Data vs. Quality Control Measurements 5 years 5 months ago #17175

  • Cynthia Lim Louis, PMP
  • Cynthia Lim Louis, PMP's Avatar
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 84
  • Karma: 5
  • Thank you received: 21
I don’t understand your question. Are you asking whether there is a difference between quality metrics and quality control measurements in Manage Quality process?

Quality Data vs. Quality Control Measurements 5 years 5 months ago #17178

  • Ben Chalfie
  • Ben Chalfie's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 41
  • Thank you received: 0
No, sorry. What are quality metrics compared with during Performance Reviews in the Control Quality process? What are the actual results" the PMBOK is references in the attached PMBOK page (303). And how do those "actual results" compare with the quality control measurements?
Attachments:

Quality Data vs. Quality Control Measurements 5 years 5 months ago #17203

  • Cynthia Lim Louis, PMP
  • Cynthia Lim Louis, PMP's Avatar
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 84
  • Karma: 5
  • Thank you received: 21
Thanks for the clarifying your question.

In Control Quality process, the aim is to ensure that the deliverable meet all standards, requirements and customer expectation. During performance review, quality metrics outlined in the Quality Management Plan (see pages 286-287) are compared against the actual results. The actual results can be a weekly status report that showed the actual number of products produced versus the actual number of defects per day or the process of ensuring the project is conducted according to requirements, etc.

For Quality Control Measurements, look at the definition in both Manage Quality and Control Quality processes. For example, in Manage Quality process, you use these measurements to determine whether your product is correct per requirement while in Control Quality process, it is the documented results of the Control Quality activities (e.g., inspection).

Quality Data vs. Quality Control Measurements 4 years 5 months ago #20743

  • Mamdouh
  • Mamdouh 's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
hi synthia,
follow up question, what's the difference between quality reports (output from manage quality) and quality control measurements? i look in pmbok for their definitions and i got the difference between them. no need any clarification.
thank you.
mamdouh
Last edit: by Mamdouh .
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login