In the context of the following question,

If you are executing the control procurement process if there is an issue with a delivery of material which is the responsibility of your supplier, what tools can determine if corrective actions are needed?
Inspections or Audits?

I think both may be correct, but the answer key prefers the latter. Not sure why. Can someone weigh in, please?

Audit vs Inspection 7 months 1 week ago #17159

  • Cynthia Lim Louis, PMP
  • Cynthia Lim Louis, PMP's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 84
  • Karma: 3
  • Thank you received: 17
Inspections are usually performed by the contractor or together with you (e.g., a walk through process on how their materials are manufactured). During contractor's inspection of the material, the contractor finds that the material is out of scope, he will submit a change request and carry out the corrective actions to ensure that the materials are per your requirement.

In this context, as a customer you would audit the procurement process, e.g., whether the corrective actions are implemented.
Moderators: Yolanda MabutasScott GillardMary Kathrine PaduaCynthia Lim Louis, PMPTracy Shagnea, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinAmy MartinezEmily RiveraLisa Sweeney PMPHarry ElstonMani Selvan

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login