fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Network Diagrams

Network Diagrams 5 years 1 month ago #16888

  • Jeanie Burdi
  • Jeanie Burdi's Avatar Topic Author
  • Visitor
  • Visitor
Hello,
I'm a new customer to you all ...but I have been doing scheduling since 2003.
I have a question on Network/PERT diagrams.
I'm watching L06.05: Develop Schedule - Part 3, and noticed on your network diagram, activity A has a 5 day duration and the Start is 0 Finish is 5. It has a successor of B with a 2 day Duration, FS. Activity B has a Start of 5 and a Finish of 7. I have seen training videos where B would have a start of the next day...Start would be 6 and Finish on 8. Which is the right way to do this?
I ask...because in a schedule, you finish an activity, the successor doesn't start until the next day (unless you have weird calendar setup issues). If you have 100 activities...this could mean 100 day there is a 100 day delta between what you expect from the Network diagram and what is real, schedule.

I have been trying to figure this out for a while. I am training a young man in another country (via Instant Messaging) and I went back and forth on trying to explain this.

Any help you can provide would be great. Thank you so much.

Jeanie Burdi

Network Diagrams 5 years 4 weeks ago #16899

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Away
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1982
  • Karma: 119
  • Thank you received: 606
Jeannie,

I'm looking into this. Give me a couple of days to review it.
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
The following user(s) said Thank You: Jeanie Burdi

Network Diagrams 5 years 1 week ago #17079

  • Jeanie Burdi
  • Jeanie Burdi's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Be Passionate
  • Posts: 7
  • Thank you received: 0
Was wondering if you found an answer to this?
The graveyard is filled with important men, who could not be spared....
but were... in the end.
Jeanie Burdi

Network Diagrams 4 years 11 months ago #17504

  • Jeanie Burdi
  • Jeanie Burdi's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Be Passionate
  • Posts: 7
  • Thank you received: 0
What is the verdict?
The graveyard is filled with important men, who could not be spared....
but were... in the end.
Jeanie Burdi

Network Diagrams 1 year 6 months ago #29888

  • Anonymous
  • Anonymous's Avatar Topic Author
  • Visitor
  • Visitor
Any update?

Network Diagrams 1 year 6 months ago #29889

  • Jeanie Burdi
  • Jeanie Burdi's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Be Passionate
  • Posts: 7
  • Thank you received: 0
Hello,
I was wondering what the answer to this is.
"Hello,
I'm a new customer to you all ...but I have been doing scheduling since 2003.
I have a question on Network/PERT diagrams.
I'm watching L06.05: Develop Schedule - Part 3, and noticed on your network diagram, activity A has a 5 day duration and the Start is 0 Finish is 5. It has a successor of B with a 2 day Duration, FS. Activity B has a Start of 5 and a Finish of 7. I have seen training videos where B would have a start of the next day...Start would be 6 and Finish on 8. Which is the right way to do this?
I ask...because in a schedule, you finish an activity, the successor doesn't start until the next day (unless you have weird calendar setup issues). If you have 100 activities...this could mean 100 day there is a 100 day delta between what you expect from the Network diagram and what is real, schedule.

I have been trying to figure this out for a while. I am training a young man in another country (via Instant Messaging) and I went back and forth on trying to explain this.

Any help you can provide would be great. Thank you so much.

Jeanie Burdi"
The graveyard is filled with important men, who could not be spared....
but were... in the end.
Jeanie Burdi
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login