fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Quality audits

Quality audits 5 years 3 months ago #16363

  • Julia Soligo
  • Julia Soligo's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 12
  • Thank you received: 0
Hi,
I found this question on Oliver F. Lehmann prep test (200 questions document):

116. A project customer and a contractor agreed on regular quality audits during execution by a third party audit team, which is working on an assignment for the customer.
What should the contractor have prepared for the audits?
o Work results
o Measurements and test results
o Quality documentation
o Contract-related correspondence

Correct answer is (C), Quality documentation, and it refers to PMBOK pages 294-295 where Audits are defined. In my opinion, a quality team could audit many things regarding the contractor work, so I don't completely understand why only answer (C) is correct, I believe answers (A) and ( B ) could be correct too.

Would like yo know your thoughts. Thanks!
Julia
Last edit: by .

Quality audits 5 years 2 months ago #16442

  • Joe Pang
  • Joe Pang's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 250
  • Karma: 24
  • Thank you received: 99
Hi Julia,

Do remember that Quality Audits are targeted towards improving the processes/best practices. Therefore, while providing A) Work Results and B ) Measurements and Test Results is crucial to a Quality Check, they do very little for the benefits of a Quality Audit.

Hope this helps
Toronto-based project manager, I specialize in capital construction projects and digital transformation projects for the power & utility sector.

I welcome all types of collaboration opportunities, feel free to connect with me on Linkedin
Last edit: by Joe Pang.

Quality audits 5 years 2 months ago #16450

  • Julia Soligo
  • Julia Soligo's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 11
  • Thank you received: 0
Thank you very much!
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login