Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Open ended activity ("dangle")

Open ended activity ("dangle") 7 years 10 months ago #16358

  • Julia Soligo
  • Julia Soligo's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 12
  • Thank you received: 0
Hi,

Could you please explain the attached question with diagram, and the concept of Open ended activity ("dangle") . Correct answer is (A).
Thanks!

Julia
Attachments:

Open ended activity ("dangle") 6 years 1 day ago #24637

  • VINCENT GANGULA
  • VINCENT GANGULA's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
Dangling activities (also known as dangles) are loosely-tied activities in project schedules. They are activities with either open start dates or open end dates. All activities, except the first activity of a network, need to have a predecessor; otherwise, they will have open start dates.

Open ended activity ("dangle") 5 years 10 months ago #25544

  • Dangle
  • Dangle's Avatar
  • Visitor
  • Visitor
Activity F will start when activity E has reached 40% but there is no incentive of finishing activity E as there is nothing attached to its completion. The relationship is for its 40% completion so that activity might be get lost.
Moderators: Yolanda Mabutas, Markus Kopko, Mary Kathrine Padua, Professor Kevin Reilly, John Paul Bugarin, Anusha Jayaram, Harry Elston, Jean Kwanda, Neil Baghurst PMP, Elena Zelenevskaia, Erik Smith, Joseph Flanders, Pablo Andres Loayza

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login