3 years 3 months ago #25544

Dangle

's Avatar

Activity F will start when activity E has reached 40% but there is no incentive of finishing activity E as there is nothing attached to its completion. The relationship is for its 40% completion so that activity might be get lost.
3 years 4 months ago #24637

VINCENT GANGULA

VINCENT GANGULA's Avatar

Dangling activities (also known as dangles) are loosely-tied activities in project schedules. They are activities with either open start dates or open end dates. All activities, except the first activity of a network, need to have a predecessor; otherwise, they will have open start dates.
5 years 2 months ago #16358

Julia Soligo

Julia Soligo's Avatar

Hi,

Could you please explain the attached question with diagram, and the concept of Open ended activity ("dangle") . Correct answer is (A).
Thanks!

Julia