Reply: Perform Integrated Change Control - Change Request Sequence

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : Perform Integrated Change Control - Change Request Sequence

Max. showing the last 6 posts - (Last post first)
6 years 1 month ago #13336

Ty Weston, PMP

Ty Weston, PMP's Avatar

If it has an impact to baselines, then it probably will go to a change control board, who will need to know all the information and impacts to the project. You need to make sure you provide all the facts and impacts, so analysing would come prior to submitting the entire change control request. Plus you will have to determine if the change request meets the criteria, if any, for the request.
6 years 1 month ago #13335

Femi Shodeinde

Femi Shodeinde's Avatar

In PICC, Change Request Sequnce, which comes first when asked by stakeholder to initiate a CR? Immediately submit CR or analyze impact to baselines?