fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Perform Integrated Change Control - Change Request Sequence

Perform Integrated Change Control - Change Request Sequence 6 years 1 month ago #13335

  • Femi Shodeinde
  • Femi Shodeinde's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 0
In PICC, Change Request Sequnce, which comes first when asked by stakeholder to initiate a CR? Immediately submit CR or analyze impact to baselines?

Perform Integrated Change Control - Change Request Sequence 6 years 1 month ago #13336

  • Ty Weston, PMP
  • Ty Weston, PMP's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 207
  • Karma: 1
  • Thank you received: 37
If it has an impact to baselines, then it probably will go to a change control board, who will need to know all the information and impacts to the project. You need to make sure you provide all the facts and impacts, so analysing would come prior to submitting the entire change control request. Plus you will have to determine if the change request meets the criteria, if any, for the request.
Last edit: by Ty Weston, PMP.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login