Sorry I attached the wrong diagram. The question came from Oliver Lehman's 75 free sample questions # 31. His answer is 37 days. I have attached the right diagram. Thank you for your explanation.
In ref to 1st post, when activities have FF relationship we need to consider larger duration due to overlapping each other: Activity 1 (20 d)+ Activity 2 (10-2 =8 d+3 )+ Activity 4 (6 d) = 37 days.
In ref to the attached PDF, the correct answer is "B".