fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Duration question

Duration question 6 years 2 months ago #13130

  • Rosa Baumgarten
  • Rosa Baumgarten's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 5
  • Thank you received: 1
Can someone help explain the correct answer ?

Activity 1 has a duration of 20 days, activity 2 of 10 days, activity 3 of 5 days and activity 4 of 6 days.

with the following path

MILSTONE A --FS-- -ACTIVITY 1 ---FS ---ACTIVITY 2 ----FF-2days
ACTIVITY 3---FS +3 days
ACTIVITY 4----FS----MILESTONE B

What is the minimum total duration between the milestones A and B?



36 days
37 days
39 days
42 days

Why is the answer 37 days?

Duration question 6 years 2 months ago #13175

  • Steven Mudrinich, PMP
  • Steven Mudrinich, PMP's Avatar
  • Offline
  • Expert Boarder
  • Expert Boarder
  • Posts: 126
  • Karma: 7
  • Thank you received: 25
Rosa,

I suspect you haven't received an answer yet because your question is a little difficult to comprehend. Can you display the schedule problem as a graphic? This would help us better visualize it and work out a solution for you. Thanks!

- Steven

Duration question 6 years 2 months ago #13246

  • Rosa Baumgarten
  • Rosa Baumgarten's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 5
  • Thank you received: 1
I have attached a PDF of the diagram to help with the question.

Thank you
Attachments:

[email protected] 6 years 1 month ago #13359

  • Anonymous
  • Anonymous's Avatar
  • Visitor
  • Visitor
In ref to 1st post, when activities have FF relationship we need to consider larger duration due to overlapping each other: Activity 1 (20 d)+ Activity 2 (10-2 =8 d+3 )+ Activity 4 (6 d) = 37 days.

In ref to the attached PDF, the correct answer is "B".
Thanks,

Mahabub

Duration question 6 years 1 month ago #13364

  • Rosa Baumgarten
  • Rosa Baumgarten's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 5
  • Thank you received: 1
Sorry I attached the wrong diagram. The question came from Oliver Lehman's 75 free sample questions # 31. His answer is 37 days. I have attached the right diagram. Thank you for your explanation.

Duration question 6 years 1 month ago #13365

  • Tracy Shagnea, PMP
  • Tracy Shagnea, PMP's Avatar
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 134
  • Karma: 7
  • Thank you received: 46
Rosa,

I don't see the attachment you referenced in your latest post.

Tracy
Forum Moderator
PMP, CSM, M.S. Management
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login