TOPIC: Duration question

Duration question 1 year 7 months ago #13130

  • Rosa Baumgarten
  • Rosa Baumgarten's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 5
  • Thank you received: 1
Can someone help explain the correct answer ?

Activity 1 has a duration of 20 days, activity 2 of 10 days, activity 3 of 5 days and activity 4 of 6 days.

with the following path

MILSTONE A --FS-- -ACTIVITY 1 ---FS ---ACTIVITY 2 ----FF-2days
ACTIVITY 3---FS +3 days
ACTIVITY 4----FS----MILESTONE B

What is the minimum total duration between the milestones A and B?



36 days
37 days
39 days
42 days

Why is the answer 37 days?

Duration question 1 year 7 months ago #13175

  • Steven Mudrinich, PMP
  • Steven Mudrinich, PMP's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 125
  • Karma: 4
  • Thank you received: 21
Rosa,

I suspect you haven't received an answer yet because your question is a little difficult to comprehend. Can you display the schedule problem as a graphic? This would help us better visualize it and work out a solution for you. Thanks!

- Steven

Duration question 1 year 7 months ago #13246

  • Rosa Baumgarten
  • Rosa Baumgarten's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 5
  • Thank you received: 1
I have attached a PDF of the diagram to help with the question.

Thank you
Attachments:

[email protected] 1 year 6 months ago #13359

  • Anonymous
  • Anonymous's Avatar
  • Visitor
  • Visitor
In ref to 1st post, when activities have FF relationship we need to consider larger duration due to overlapping each other: Activity 1 (20 d)+ Activity 2 (10-2 =8 d+3 )+ Activity 4 (6 d) = 37 days.

In ref to the attached PDF, the correct answer is "B".
Thanks,

Mahabub

Duration question 1 year 6 months ago #13364

  • Rosa Baumgarten
  • Rosa Baumgarten's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 5
  • Thank you received: 1
Sorry I attached the wrong diagram. The question came from Oliver Lehman's 75 free sample questions # 31. His answer is 37 days. I have attached the right diagram. Thank you for your explanation.

Duration question 1 year 6 months ago #13365

  • Tracy Shagnea, PMP
  • Tracy Shagnea, PMP's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 110
  • Karma: 6
  • Thank you received: 42
Rosa,

I don't see the attachment you referenced in your latest post.

Tracy
Forum Moderator
PMP, CSM, M.S. Management
Moderators: Yolanda MabutasScott GillardMary Kathrine PaduaSteven Mudrinich, PMPCynthia Lim Louis, PMPTracy Shagnea, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinJason YorekLuke HoSimone ChristieAmy MartinezDaniel DewartEmily RiveraMani Selvan

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login
Boost Your PMP Exam Prep in Only Eight Hours! Join the Live PMP Coaching Class on September 21/22 for just $179. Click to learn more... OR Click to watch a free session...