Hi,
I have completed a significant investment of time into three projects over the last 8 years but they were all cancelled at various stages. For example, we started a project to implement a new system and then mid-way through controlling/monitoring period it was cancelled. Another project we completed the selection of the application and went to contract but leadership cancelled it before we implemented the solution. We were able to complete the selection of the tool but not the implementation. And lastly there was a project to develop a business case. The business case was completed but the application was not funded so it did not go to the next project phase. All of them would total 870 hours or more. I had a lead role to make sure all of these get done and then had to close out the projects.
Thank you,
Stephanie