Reply: Calculating Duration on a Network Diagram

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : Calculating Duration on a Network Diagram

Max. showing the last 6 posts - (Last post first)
6 years 5 months ago #12281

Tracy Shagnea, PMP

Tracy Shagnea, PMP's Avatar

Maryann,

It depends on the method used to create the network diagram. Check out Cornelius' response here:

https://www.project-management-prepcast.com/kunena/pmp-exam-discussion/3099-cpm-calculations-start-with-day-0-or-day-1

Best wishes,

Tracy
6 years 5 months ago #12280

Maryann Von Roth

Maryann Von Roth's Avatar

The map cannot be displayed, you haven't specified a location yet.
Hi!
For the Exam, is Duration calculated as

EF-ES = Duration or
EF-ES +1 = Duration?
I used #1 on a trial test question and got it wrong. I see it both ways in various presentations and learning tools.